Järvenpää CHP Project - HP piping.

Information

Förhandlat förfarande
2012-02-24 04:17 (GMT+01:00)

Inköpare

Fortum Power and Heat Oy Fortum Power and Heat Oy
PL 100
00048 Fortum
Finland

Tilldelningsinformation

Fortum Power and Heat Oy is planning to improve the existing district heat production capacity by installing a new combined heat and power plant (the CHP Plant) to cover the base district heat load of the city of Järvenpää, Finland.

The power plant concept consists of 76 MW fuel-power BFB boiler plant and 23 MW electric power steam turbine generator plant. The new plant is planned to be in commercial operation in the middle of year 2013.

This supply consists of high pressure piping including material, prefabrication and installation.

Section V: Award of contract

V.1.1) Date of contract award decision:

14.2.2012

V.1.2) Information about offers

V.1.3) Name and address of economic operator in favour of whom the contract award decision has been taken

YIT Teollisuus Oy

Mercell Commerce

Del av Mercellgruppen, en av Europas ledande leverantörer av elektroniska upphandlings- och anbudssystem på den professionella marknaden.

Kontakta oss

Klicka här för att gå till vår support

+46 077 144 02 00
Mercell Commerce | Lindhagensgatan 94, 11218 Stockholm, Sverige